Write Your Quotes So The Job Can't Come Back On You

The number is the smallest part of a quote. The scope, the exclusions and the change-order line are what keep a good job from turning into a fight.

By Ray Okonkwo · Money & Business6 min read
Share

The argument never happens on day one. It happens on day nine, when the deck's framed, the customer's brother-in-law has walked the site, and somebody says the word "included."

You can win that argument in about forty seconds, or you can lose a weekend and a thousand dollars to it. The difference is what you typed into a document two weeks earlier while you were tired and wanted to get the number out the door.

A quote isn't a sales sheet with a price on the bottom. It's the fence around the work. Everything inside the fence you do for that money. Everything outside it costs more. If the fence is fuzzy, the customer gets to decide where it sits, and they won't decide in your favor.

Say "estimate" only when you mean it

An estimate is your best guess. A quote is a price you're standing behind. People use the words interchangeably and then get confused when the invoice doesn't match.

Pick one, label it at the top in bold, and mean it. If you write Fixed price quote on a bathroom rebuild and then discover the subfloor is rotten, you eat it unless you excluded it. If you write Estimate and treat it like a blank check, you'll lose the customer and probably the review.

Most small shops should be quoting fixed prices on defined work and estimating only on genuine unknowns like drain clearing or diagnostic work. Customers trust a fixed number. It's also the fastest way to get paid, because there's nothing to itemize and dispute at the end.

One caveat worth money: consumer contract rules vary by state, and some states have specific requirements for home improvement contracts, deposits, and cancellation windows. Have an attorney in your state read your template once. A couple hundred dollars, one time, and then you use it for the next five years.

Scope is nouns and numbers

"Paint the living room" isn't scope. It's a wish.

Scope reads like this: two coats of interior latex on walls only, approximately 420 square feet, one accent wall in a second color, ceilings and trim not included, customer selects colors from the manufacturer's standard line by the Friday before start.

Notice what's in there. A quantity. A count. A material grade. A deadline that belongs to the customer, not you.

Write every line so a stranger could walk in with your sheet and tell whether the work is done. If a line can't be checked off, rewrite it. "Clean up daily" is checkable. "Leave the site tidy" is a debate.

The exclusions list is where your margin lives

This is the part everybody skips, and it's the part that saves jobs.

Under a heading that says Not included in this price, list the things a reasonable person might assume you're doing:

  • Permits and permit fees
  • Repair of anything found behind existing surfaces
  • Removal of appliances, furniture, or customer property
  • Dumpster or disposal of materials you didn't bring
  • Electrical or plumbing modifications
  • Painting after the work
  • Matching existing finishes that are discontinued

That last one has burned more remodelers than bad math. Somebody wants three tiles replaced and the tile hasn't been made since 2009.

Exclusions don't make you look negative. They make you look like you've done this before. Customers read a specific exclusion list and think "this guy knows what goes wrong." The vague quote from the other bidder starts looking like a trap, because it's.

Assumptions are exclusions with better manners

Write a short block that starts: This price assumes.

Assumes clear access to the work area. Assumes water and 120V power on site. Assumes work between 7 a.m. and 5 p.m., Monday through Friday. Assumes existing framing is sound. Assumes one mobilization, not two.

Then one sentence to close the loop: if any assumption turns out to be wrong, you'll stop, price the difference in writing, and wait for approval before continuing.

That sentence is the whole ballgame. It converts an ugly surprise from a fight into a piece of paperwork.

Use allowances for things they haven't picked yet

Customers love to sign before they've chosen fixtures. Fine. Give them an allowance.

"Includes a $600 allowance for the vanity and faucet. Cost above or below the allowance is adjusted on the final invoice at cost."

Say whether the allowance covers tax and delivery, because it should, and because that's the line people argue about. And put the supplier reference in there if you can. An allowance at a contractor supply house and an allowance at a boutique showroom aren't the same money.

Change orders, written and signed, before the tools come out

The rule that keeps you out of court: no extra work starts until the extra work is priced and approved in writing.

Keep it stupid simple. A one-page form, or honestly a text message with a photo, the description, the dollar amount, and a "yes" typed back. Say in the quote that email or text approval counts as a signature, and then it does.

The temptation is always to do the little extra as a favor. Add the outlet. Haul the old grill. That's fine once, and it's good business. But the second you're at four hundred dollars of favors, put it on paper anyway and mark it no charge. Now the customer sees the value instead of assuming it was free all along, and you've set the precedent that extras get documented.

Payment terms people actually follow

Name the dollar amounts and the dates, not the concepts.

A deposit at signing. A progress payment at a milestone a customer can see, like "rough-in complete," not "50 percent complete," because nobody agrees on what 50 percent looks like. Balance due on completion, and define completion. Say what methods you accept and which ones cost extra. Say what happens if it's late.

If you're doing work over a few thousand dollars, know the mechanic's lien rules in your state, including the notice you may have to send at the start of the job to preserve the right. Miss that window and the lien is gone. Your attorney covers this in the same conversation as the template.

Put a shelf life on the number

This quote is valid for 30 days. Material prices move, your schedule fills, and somebody will absolutely call in March holding a quote you wrote in September and expect the September price.

Thirty days is standard. Seven is fine on volatile materials if you say why.

Before you start, take the photos

Twenty pictures on your phone, timestamped, before a single tool comes off the truck. The scuffed baseboard. The crack in the driveway. The dead spot in the lawn by the gate.

Costs you four minutes. The one time it matters, it's worth more than your insurance deductible.

And when you get the number wrong anyway

You will. Everybody does. Not because of the customer, but because you measured the wrong wall or forgot that the truck can't get down that alley.

Don't hide it, and don't quietly cheapen the job to claw it back. That's how good trades get bad reputations. Either eat it and log what it cost you, or go to the customer early, explain plainly what you missed, and offer to split it. Early and honest gets you a deal about half the time. On day nine, it gets you nothing.

Write the version of the quote you'd want to be holding at 9 p.m. on that ninth day. Then send that one.

Share this article

Ray Okonkwo

Money & Business

Former commercial banker turned small-business owner. Covers salary, credit, margins and the arithmetic nobody does before signing.

Watch

Worth an hour of your evening

More from Startups.

From channels we rate. Plays on YouTube.

    Alex Hormozi24 Sept

    How Anything Scales: Start, Compound, Augment, Leverage, Expand

    Alex Hormozi24 Sept

    No One Taking You Seriously Is Your Greatest Advantage

    Alex Hormozi24 Sept

    If You Fall in Love with Getting Better, You Become Very Hard to Beat

    Greg Raiz30 Dec

    How to Bootstrap a Business