Write the price spike into the contract before it happens
A fixed price is a bet on your supplier's next quote. Six clauses decide whether you or your customer carries the risk when it moves.

Quick answer: Tie your price to a dated supplier quote that expires. Add an adjustment clause with a trigger and a published index. Make customer delays the customer's cost. Collect a deposit big enough to buy the volatile materials early. Then have a lawyer licensed in your state read the final wording, because this is general education, not advice on your contract.
The quote is the weak point
Say you bid a $212,000 addition in March. Framing lumber and copper wire are priced off a supplier quote that was good for two weeks. The customer takes six weeks to sign. Permits take two more months. By the time you order, the materials line you priced at $48,000 is $58,000.
The contract says "fixed price." That ten grand is yours.
Nobody did anything wrong. The bid was honest and the customer was reasonable. The contract just never said who owns the gap between the day you priced it and the day you bought it. When a contract is silent, the risk stays with whoever signed a fixed number, and that's you.
Waiting for someone to rescue you is not a plan. The wording below is how you carry your own weight without carrying somebody else's.
Clause one: a price that expires
Attach the supplier quote to the bid and state its date. Then write that your price holds for a set number of days, say 30, from the bid date. If the customer signs after that, you reprice the materials at current cost before work is scheduled.
This is the cheapest protection you have, and most small shops skip it. It costs you nothing but a sentence. It also teaches customers that your number has a shelf life, which is true of every number in construction.
Clause two: an adjustment with a trigger
Fixed price doesn't have to mean frozen price. A material adjustment clause says that if the documented cost of named materials rises more than a set percentage from the quoted cost, the contract price rises by the difference.
Three pieces make it work:
- A threshold. Pick a number, such as 5 percent on a named material. Small swings stay your problem, and the customer sees you aren't nickel-and-diming.
- A measuring stick. Either your supplier invoices or a published index. The Bureau of Labor Statistics publishes Producer Price Index series for materials like steel mill products and lumber. An index is harder to argue with than your word.
- Proof. You send the invoice or index reading along with the request. No paperwork, no adjustment.
Make it run both ways. If prices drop below the threshold, the customer gets the credit. A clause that only moves in your favor reads like a trap, and sensible customers won't sign it. A two-way clause reads like fairness.
Clause three: only the materials that bounce
Don't put the whole job under the adjustment. List the two or three line items that actually swing, such as lumber, copper, steel, or asphalt, and attach the dollar quantities. Everything else stays fixed.
Naming quantities matters. If the clause says "lumber" and the job ends up needing twice as much because of a design change, you want the change order to handle that, not an argument about a percentage.
Clause four: buy early, and get paid to
The simplest hedge is to stop being exposed. A deposit clause lets you order the volatile materials at signing, with the deposit sized to cover them. Once they're bought, the price spike belongs to the supplier, not the job.
Pair that with a stored-materials clause. If the lumber is sitting in your yard or a supplier's warehouse, you may bill for it when it's purchased and protected, with an invoice and a photo as backup. Without that line, you're floating five figures of the customer's materials on your own credit.
The trade-off is real. Customers don't love paying for wood they can't see in a wall. Offer a materials-only receipt and a clear refund path if the job dies before work starts. Most will accept it.
Clause five: their delay, their cost
Price holds depend on a schedule. Write that if the start date slips for reasons outside your control, the price hold slips with it. That covers late permits, late customer decisions, late payments, and site access problems.
Be specific. "Delays caused by owner" is vague. "Any delay longer than 14 days in owner approvals, permits obtained by owner, or site readiness" gives a judge, or better yet your customer, something to read.
Clause six: notice, then options
A spike doesn't help you if you announce it after the bill is paid. Require written notice within a set period, often 7 to 10 days, of learning about the increase. Attach the proof. Then give the customer a choice in writing:
- Approve the increase.
- Approve a substitute material of equal quality, if one exists.
- Pause or end the contract, paying for work completed and materials already bought.
That third option is what separates a clause from a threat. You aren't forcing the customer to eat the cost. You're giving them a way out that doesn't leave you holding the bill.
Add a line for outside events too. Tariffs, new regulations, or a supplier going out of business can change a price overnight. Say whether those fall under the adjustment clause or give either side a right to renegotiate.
What to say when the customer pushes back
They'll ask why they should carry your risk. Tell them the truth: you could pad the bid by 10 percent to cover the chance of a spike, and they'd pay it whether or not it happened. The clause means they pay only if it does. It's the lower-cost way to buy the same protection.
Some will still walk, and the competitor who bid fixed with no clause may win the job. Let him. If he's wrong about lumber, he'll find out, and the job gets ugly in month three. Know your floor, and know the price at which a job loses money. Your weekly numbers tell you what that is before you sign instead of after.
A few cautions:
- Public and large commercial work often brings its own price-adjustment terms. Read them before you add yours.
- Some states regulate residential construction contracts, including deposit limits. Don't assume your deposit clause is legal as written.
- A clause you can't explain in two sentences is a clause you'll lose an argument over.
After the signature
Contract language only works if you use it. Calendar the quote expiration date. Send the notice the day you see the invoice. Keep your supplier quotes in the job file. Check each month whether the materials line is moving, and your monthly profit and loss will show a squeeze before it becomes a loss.
And collect on the adjustment promptly. An approved increase left sitting on an invoice is the same problem as any late payment: a process failure that looks like a people failure.
Spend an hour and a few hundred dollars with a contract attorney this quarter, bring your last three jobs, and ask which of these clauses fit your state and your trade. It's cheaper than the next spike.
Ray Okonkwo
Money & Business
Former commercial banker turned small-business owner. Covers salary, credit, margins and the arithmetic nobody does before signing.
Watch
Worth an hour of your evening
More from Business.
From channels we rate. Plays on YouTube.
Read next