Write the delay clause before the job starts running late

Every job that slips is a fight over who pays for the days. Settle it in the contract, while everybody still likes each other.

By Ray Okonkwo · Money & Business6 min read
Write the delay clause before the job starts running late

Quick answer: Sort every possible delay into three buckets: yours, the client's, and nobody's. Put a price and a rule on each one before work starts. Then require signed paper for every change, with both a dollar amount and a number of days.

The job was quoted at six weeks. It's week nine. The tile is stuck at a distributor, the homeowner just asked for a second window, and your framing crew spent four days on another site because that job's inspector didn't show. Nobody did anything outrageous. Everybody is irritated anyway.

That's a normal bad job, and most contracts say almost nothing about it. They state a price and a target date, then go quiet on the one question that will actually come up: who eats the cost of the extra time.

Sort delays into three buckets

Every overrun has a cause, and every cause belongs to somebody.

Yours. Your crew was late, you under-ordered, you scheduled two jobs on the same week. You own this. A good contract doesn't pretend otherwise, and you shouldn't want it to. If you can't take the heat of being held to a date, don't promise the date.

Theirs. The client changed the layout, picked a finish that's backordered, wasn't home to give access, or paid late. This is where most contractors get burned, because they absorb it quietly for three weeks and then bring it up in a heated phone call.

Nobody's. Weather. A supplier shutdown. A permit office running behind. A utility that moves the shutoff date. Nobody earned this one, so the contract has to say how it's shared. The usual answer: the completion date moves day for day, and neither side bills the other for the wait.

Write those three buckets into the agreement in plain words. Two paragraphs does it. If you need a page of legal Latin to say "your delay, my delay, nobody's delay," you've hired the wrong template.

Make every change a signed change

Scope creep doesn't arrive as a big demand. It arrives as "while you're in there, could you."

You say yes because it's ten minutes and the client is nice. Then it's ten minutes forty times.

The fix is a change-order clause with one rule: nothing outside the original scope gets done until both sides sign a short form stating the added price and the added days. Most people price the change and forget the time. That's the mistake. A $900 add-on that pushes the finish back eight days has a cost the $900 doesn't cover, because your crew is now unavailable for the next job.

A text thread can count if the contract says it does and both of you confirm the number in writing. A verbal "sure, go ahead" counts for nothing when the final invoice lands.

And you'll feel awkward the first time you say, "Happy to do it, let me send you the one-page change form." Say it anyway. The awkwardness lasts a minute. The alternative lasts until the final payment.

Tie payments to work done, not dates passed

If your draws are calendar-based, a delay that isn't your fault starves your cash flow while your costs keep running. You're paying wages on a job that isn't paying you.

Tie each payment to a stage of completed work: deposit, materials delivered, rough-in done, substantial completion, final. When the job slows for a reason outside your control, the money only slows with the work, instead of leaving you financing the client's decisions.

Put the invoice terms in the same document: due on receipt or net ten, whatever you choose, plus what happens if it's missed. Most of the late-payment trouble comes from a vague process, which is its own topic, covered in most late invoices are a process problem, not a people problem.

What the delay clause should actually say

Keep it short and specific. At a minimum:

  • Notice. Whoever sees a delay coming tells the other in writing within two business days. A delay nobody mentioned until week nine is hard to argue about fairly.
  • What counts as excusable. Name the usual suspects: weather, supplier shortages, government or utility delays, client changes, client's late access or payment.
  • Time extension. Each excusable day moves the completion date a day.
  • Standby cost. If the client's delay leaves your crew idle, a stated daily rate applies. Pick a number that covers real wages and overhead, not a punishment.
  • Right to pause. If a payment is more than a set number of days late, you can stop work without penalty until it's caught up.
  • Material price swings. For long jobs, say who takes the hit if a major material jumps in price before you buy it. Allowances for items the client picks, like fixtures and flooring, keep this clean.
  • Your own late finish. If you're penalizing yourself with a per-day credit for your delays, keep it modest and capped. A clause with no cap is a trap you set for yourself.

Have a local attorney read the final version. Rules on home-improvement contracts, lien rights and payment timing vary by state, and some states require specific language. An hour of a lawyer's time on your template costs far less than one disputed job.

Fixed price, time-and-materials, or the middle

Fixed price feels safe, and for the client it is, because you carry the overrun risk. That's fine on a well-defined job where you've done the same thing twenty times. It's a bad deal when the scope is fuzzy or the site has surprises behind the walls.

Time-and-materials flips it. The client carries the risk and you carry less. Clients dislike the open-ended feel, and fair enough.

The middle works better than people expect: a fixed price for the defined scope, allowances for client-chosen items, unit prices for the likely unknowns (rotted subfloor at so much per square foot, extra footings at so much each), and a change order for everything else. Both sides can see the exposure up front.

If you're the one hiring, ask for that structure. A contractor who offers it isn't padding the bid. He's telling you where the real risk sits.

Keep the paper trail while the job is alive

Disputes get decided on records, not on who's louder. Keep a short daily log: who was on site, what got done, what blocked you, what the client asked for. Take photos. Save the texts. It takes five minutes before you pack up for the day.

Then watch the job's actual cost against the bid every week instead of finding out at the end. Read your own profit and loss in ten minutes a month covers the monthly view, and the weekly numbers that keep a small business out of trouble covers the weekly one. A job bleeding days will show up in both long before the client complains.

Hold the line, then be generous where you can afford it

A contract isn't a weapon, and it isn't a substitute for character. It's what two honest men agree to while they still trust each other, so neither has to guess later.

Enforce the big items: signed changes, notice of delays, payment on schedule. Let the small ones go. If the client's cousin held up access for half a day, eat it and say so. Goodwill spent on purpose is cheap.

Then finish the job. Sweep the site, haul your own debris, walk the punch list with the owner before he has to ask. The contract settles who pays for the time. How you leave the place settles whether he calls you next spring.

Ray Okonkwo

Money & Business

Former commercial banker turned small-business owner. Covers salary, credit, margins and the arithmetic nobody does before signing.

Watch

Worth an hour of your evening

More from Business.

From channels we rate. Plays on YouTube.

    Alex HormoziNov 25

    Speak loud enough, slow enough, and clearly enough to be understood.

    Alex HormoziNov 24

    Before you launch another product line, decide who your brand is for.

    Alex HormoziNov 24

    The optimal price for a product gets far more NOs than the one that sells the most people.

    IndeedDec 27

    6 Tips For Improving Your Customer Service Skills | Indeed Career Tips