No signed estimate, no change orders

Without a signed baseline, every "while you're in there" becomes an argument about what you agreed to. Fix that before the first phone call.

By Ray Okonkwo · Money & Business6 min read
No signed estimate, no change orders

Quick answer: A change order is a change to something. If the original scope isn't signed, there's nothing to change, and every call from the customer starts a fresh negotiation. Get the estimate signed first. Then make one rule: no extra work starts until the change is written, priced and signed.

The call you already know

You quoted a bathroom at $14,200. Day three, the customer phones. "Since you've got the wall open, can you move the vanity eight inches? And I think we talked about the heated floor."

Did you talk about the heated floor? You remember a conversation in the driveway. They remember a promise. Neither of you wrote anything down, so now it's your memory against theirs, and the customer is holding the checkbook.

That argument costs you $1,800 or a bad review, usually both. It started before the first nail went in.

Why the signature comes first

Most operators treat a change order as a form to use when things go sideways. It's the opposite. It's a measuring tool, and it only measures against a fixed line.

An unsigned estimate isn't a fixed line. It's a proposal. The customer can say they never saw that page, never agreed to that allowance, or understood "tile" to mean something pricier. Once that happens, every change you try to document gets argued back to the original, and the original is mush.

A signed estimate does three jobs:

  • It fixes what's included, so extras are visibly extra.
  • It fixes the price, so nobody's arguing about the base number mid-job.
  • It sets the process, so the customer has already agreed to how changes work before they want one.

That third one is the quiet winner. You're not springing a rule on someone who's already annoyed. They signed it on day one, when everybody was friendly.

What the signed estimate has to say

Keep it to a page or two. Nobody reads eleven pages of boilerplate, and a customer who doesn't read it can claim they didn't see it.

Put in:

  • A plain scope. Name the work and name the exclusions. "Does not include moving plumbing fixtures, electrical changes, or flooring beyond the tile listed" saves you more money than any sentence in the document.
  • Allowances in dollars. If tile is an allowance, write the number per square foot. Everything over it is the customer's choice and cost.
  • The price and the payment schedule. Deposit, milestones, final payment.
  • The change clause. Two or three sentences. "Any work outside this scope requires a written change order, signed by the customer, before work begins. Change orders may add cost and extend the schedule."
  • Who can sign. If a couple owns the house, one spouse says yes and the other says "I never agreed to that." Name who has authority, or get both signatures.

Rules for contracts and change orders vary by state, and many states regulate home improvement work specifically. Have a local attorney review your template once. It's a few hundred dollars well spent, not a recurring cost.

What a change order looks like

One page. Same day. Four things on it:

  1. What's changing, in a sentence or two.
  2. What it adds or subtracts, in dollars.
  3. What it does to the schedule, in days.
  4. A signature line and a date.

Write it from your phone if you have to. A photo of a handwritten page signed on the hood of a truck beats a perfect form you never got around to sending. But the signature happens before the work does. Not after, not "once the invoice goes out."

The phone call itself

The customer doesn't have to follow your system on the call. You do. Here's roughly how it sounds:

"Yes, we can move the vanity. Let me price it and get you a one-page change order today. Once you sign it, we'll schedule it in. I won't touch it before then, so nothing gets muddy for either of us."

No lecture. No tone. You said yes to the request and no to the sloppiness, and you made it sound like protection for them too. It is.

Then do the next part fast. A change order that takes you four days to send teaches the customer that the rule is a stall. Same-day turnaround makes the rule feel like service.

When they say "just do it, we'll sort it out later"

They will say it. It sounds friendly. It's the most expensive sentence in the trade.

Don't do it, and don't make it a standoff. "I'd love to. Give me ten minutes to write it up so we're both covered." Most people sign. The ones who refuse to put a $600 change on paper are telling you how the final payment conversation will go. Better to learn that on day three than on day thirty.

Hold the line, but be decent about it. If the customer's mother is in the hospital and they're stressed and wrong about the heated floor, you can be kind and still not pour concrete on a verbal promise.

The honest exceptions

Rules like this have edges, and a sensible operator knows where.

Tiny stuff. If a customer asks you to swap a cabinet pull and it costs you ten minutes, eat it. Goodwill is cheap at that scale. Set your own line, say $100 or one hour, and write the number in your own head so you apply it evenly. The risk of being walked on is real, so don't let the exception grow.

Emergencies. You open a wall and find rot or a live wire that's wrong. Safety and code don't wait on paperwork. Fix what must be fixed, photograph everything first, and get the change order signed that same day, before you go home.

Old customers. A twenty-year client who's never haggled might bristle at a form. Use it anyway, and put it on yourself: "My bookkeeper makes me do this." The paper protects the friendship as much as the job.

Make the paper a habit, not a weapon

None of this works if you wave it around like a lawsuit. The customer isn't your enemy. Most disputes aren't dishonesty. They're two people remembering the same conversation differently, and a page of paper is just a way to remember together.

Once a month, look at your jobs. How many finished at or near the signed price plus documented changes? How many had "extras" you ate? Your profit and loss will tell you the story if you read it; the walkthrough in Read your own profit and loss in ten minutes a month shows where unbilled extras hide. And if you're chasing final payments on jobs where nobody signed anything, Most late invoices are a process problem, not a people problem will sound familiar.

The conversation with the customer also gets easier when you're comfortable saying what things cost. Selling without the sales voice covers that.

Start Monday

Pull your last estimate. Does it have a scope, exclusions, allowances and a change clause? If not, rewrite it this week and have an attorney read it. Put a stack of blank change order pages in the truck.

Then the next time a customer says "while you're in there," you'll smile, say yes, and reach for a pen.

Ray Okonkwo

Money & Business

Former commercial banker turned small-business owner. Covers salary, credit, margins and the arithmetic nobody does before signing.

Watch

Worth an hour of your evening

More from Business.

From channels we rate. Plays on YouTube.

    Alex HormoziNov 21

    Because I did it that time, I can do it again.

    Alex HormoziNov 20

    Bigger houses or a bigger team. One of them has to add zeros.

    Alex HormoziNov 20

    How I'd Scale A Wedding Photography Business

    AcquisitioncomJul 1

    5 Ways to Scale ANY Business